Monday, November 22, 2010

[rti4empowerment] Re: DNA - 2010 NOV 22

 

Dear all,


In addition to the facts as mentioned below, here are some other points


The fact is, that the metro is not a tramway, and is an overhead railway, much against all sworn affidavits and claims by MMRDA, and  is proved by the statement

 Though it's a fact that the stations are right in the middle of the road, one must understand that this is the first railway project in the city after the British laid the suburban rail network over 150 years back.


And what is this formula

Civil work is just 3% of the metro construction. By October, 87% of our viaduct works have been completed, while 69% of pile caps have been done. Sixty-three per cent of piers are also ready. In the station works, 83% piles have been done, while 81% columns are ready. Construction for our car depot in DN Nagar is on in full swing. The first metro train is already in town. The second is undergoing 85 to 100 tests in China. Our transformer installation work is also on. The civil work, depot construction and other works should be complete by June next year. Work for the Andheri RoB has also started, with the railways clearing the utility shifting part.


It is left for the Citizens to add 87 per cent viaduct plus 69 per cent pile caps plus 63 per cent piers plus 83 per cent piles plus 81 per cent columns plus 1 train ready plus 1 more train undergoing 85 to 100 tests plus Railways clearing utility shifting part, whatever that means, as on 2010 NOV 21,  is equal to metro completion in 2011.

Has anyone from MMRDA or MMOPL actually seen what is the ground reality, because even the MMOPL site has been making outlandish claims since the beginning, upto 2009 JUN, last updated


And MMOPL claimed that the project will be over in 2010 JUL, now it is 2011




Before that, the tall claims was completion in 2009, starting in 2008 MAR, now it is 2011





In 2009, Metro work was to go on during monsoon, but in 2010, it is delayed due to erratic monsoon



Daily traffic disrupted for the last three years, and who knows how many more, because of totally unplanned traffic management before, and during the construction, and 

Water supply, drainage pipes damaged,  contaminating drinking water, gas lines, electricity cables, etc., on a regular basis because of total lack of any idea by MMRDA, MMOPL, MCGM, RIL, MTNL, MGL,  of where the utilities are laid underground.

Till date, the Fire Departement has no clue as to the station designs, layouts, etc., have no idea how to reach these stations, how their snorkels will be able to reach the multi storey stations, and coaches, particularly the Andheri East one, and in fact, their fire fighting capability has been substantially reduced because MMOPL has taken a considerable part of Marol Fire Station for th sub station and building.

Even E SREEDHARAN, MD, DMRC,  says that Mumbai Metro is not even half complete, costs have escalated one and a half times, and expects it to take another two years or so more to complete


Other related reports



After all this, what does MMRDA say.

Jagdeep DESAI
Architect

Secretary
Founder Trustee
Forum or Improving Quality of Life in Mumbai Suburbs

+91 98 6922 7148

>>>

>>>

'Metro I will be ready by 2011'
Published: Monday, Nov 22, 2010, 3:51 IST 
By Ninad Siddhaye | Place: Mumbai | Agency: DNA

It is probably for the first time that a top official working on the first metro corridor in the city, connecting Versova and Ghatkopar via Andheri (VAG), has spoken out against criticism levelled against the project. In an interview with DNA, Mumbai Metro One Pvt Ltd (MMOPL) director KP Maheshwari has said that the line will start running by 2011. Excerpts from the conversation:

Authorities have been at the receiving end of criticism regarding the sluggish rate at which work for the first line is going on. Some have said the corridor will not be complete before 2018. What is your response?
These allegations have very little base. I am confident that the first metro will be ready by the middle of next year. During the past 45 days or so, we have been able to mobilise huge resources to speed up work in spite of several hurdles. The monsoon has been erratic, and there have been festivals like Ganeshotsav, Navratri, Dussehra, Diwali and Eid one after the other. The market has also seen a huge shortage of sand and steel. Shortage of skilled and unskilled labour is an ongoing issue. Despite these constraints, we worked 232% faster in October than in the previous four months.

There have been allegations that authorities have not taken permissions from the fire brigade. Critics claim that the stations are designed in such a manner that fire engines will find it difficult to reach adjoining buildings in case of emergencies.
There is little truth in these allegations. First and foremost, the designs of the entire corridor have been finalised by the MMRDA [Mumbai Metropolitan Region Development Authority] and not us. Though it's a fact that the stations are right in the middle of the road, one must understand that this is the first railway project in the city after the British laid the suburban rail network over 150 years back. The significance of the metro cannot be overlooked. While constructing the stations, we have gone by the most stringent fire safety code — the National Fire Protection Association (NFPA) 130 — in the United States. Our fire safety works in three stages: prevention, detection and fire-fighting. Within the stations, we have special mechanisms to help assist the fire brigade fight fire in adjacent buildings as well.

What about the civil work? Even pillars have not been erected in some parts. What is the progress of the rail over-bridge (RoB), the most complicated part of the alignment?
Civil work is just 3% of the metro construction. By October, 87% of our viaduct works have been completed, while 69% of pile caps have been done. Sixty-three per cent of piers are also ready. In the station works, 83% piles have been done, while 81% columns are ready. Construction for our car depot in DN Nagar is on in full swing. The first metro train is already in town. The second is undergoing 85 to 100 tests in China. Our transformer installation work is also on. The civil work, depot construction and other works should be complete by June next year. Work for the Andheri RoB has also started, with the railways clearing the utility shifting part.

People often complain about the inconvenience caused by metro work.
I can only request them to bear with us. Look at New Delhi, where people suffered similar problems but their lives became easier once the metro was up and running. There is inconvenience, as the construction material and vehicles have to be stationed in the middle of important roads. Once the metro starts running, people will understand how vital it will be in changing their lives.


>>>

On Mon, Nov 22, 2010 at 12:11 PM, Nitin Killawala <nitinkill@gmail.com> wrote:

RESPONSE TO DNA ARTICLE: 22nd NOVEMBER 2010

At last we have similar views from the Concessionaire to join the bandwagon to complete the Metro-I project (now) by 2011 – only to mislead the exchequer:

 1.      ON CRITICISM OF SLUGGISH RATE OF CONSTRUCTION :

Absolutely frivolous reasons for delayed work such as Ganeshostav, Navratri, Diwali & Eid such excuses are normally given by petty road side contractors. The Building Construction industry is immune with these realities. Erratic shortage of building material, labour, etc. are all manmade and temporary. In any case Real Estate Development within the Metro Yard at Versova is coming up at brisk speed.

Comparing with your own work upto 232% faster than previous years only shows pathetic accomplishment of works in previous years.

 2.      ON FIRE SAFETY NORMS :

The CFO has clearly mentioned in their letter dated 8th March 2010 that these Fire Codes are suitable to Western Countries and culture. Therefore may not be applicable to our city especially during evacuation under panic conditions and congested traffic jams on our roads.

As mentioned "we have special mechanism to help assist the fire brigade fight fire in adjacent building as well" – is as amusing. It's like neighbours helping spontaneously Fire Brigade in recent fire at HDIL Building in Bandra.

The truth is these adjoining buildings next to Metro Stations have no access even for normal movement, leave aside Fire or any other emergencies.

3.      ON CIVIL WORK :

"Civil Work constitutes only 3% of Civil Work": If it is genuinely 3% then the entire work carried out till date is just 0.15% of the project.

I hope it's a printing error and should read 30% instead. Presuming (without admitting) entire via duct is complete with tracks, signaling and electrical/mechanical works, etc.

What about 12 Metro Stations?

Now it's a public knowledge that 4 out of these 12 stations are even in "High rise category". Cumulatively the Concessionaire needs to construct over 11 lacs sq.ft. at 12 locations in middle of busy roads. It's a matter of shame that the Concessionaire is still counting pile cap works, as "progress" after 3 years of construction, and try to justify that the Metro will run in next six months!

To conclude now it is comprehensively proved that the Metro I is not likely to see the light of the day even

after 2018 !




__._,_.___
Recent Activity:
MARKETPLACE

Stay on top of your group activity without leaving the page you're on - Get the Yahoo! Toolbar now.


Hobbies & Activities Zone: Find others who share your passions! Explore new interests.


Find useful articles and helpful tips on living with Fibromyalgia. Visit the Fibromyalgia Zone today!

.

__,_._,___

No comments:

Post a Comment