[rti4empowerment] Mumbai Suburban Railways, World Class Metro & RTI - Part III

 

Dear Friends,
 


A Brief Re-Visit to Part I & Part II


A Comprehensive Study was done in 2005

By MTR Corporation, Hong Kong At the cost of 1.5 Crore

For increasing the capacity by 1.5 to 2.25 times

of the entire Mumbai Suburban Railway (Western, Central & Harbor)

 

  • As per the Report, the Mumbai Suburban Railway can become equivalent to World Class Metro at just 1/5th of the cost of new Metro Rapid Rail Transit System
  • The Report has been hailed by All the concerned Govt. Departments - Mumbai Railway Vikas Corporation (MRVC) , Planning Commission, Various Railway Departments (Mumbai) & Railway Board (Delhi)
  •  The Report was submitted by MTR Corp. Hong Kong WAY BACK in March, 2005 to Mumbai Railway Vikas Corp., and so what is its status more than six years later in 2011? 
WHILE LAKHS (70 LAKHS) of MUMBAIKARS DAILY CONTINUE TO SAFAR (TRAVEL) IN IN-HUMAN CONDITIONS & SUFFER.
  • RTI helps in understanding the Efficacy of Decision Making Process of a (any) Government, 
  • Please read further .....

Continued Part - III
- The journey of a Railway Study Report :)


Sr.

File Movement

Date

File Movement as per the Information Provided by the

Public Information Officer under RTI as on 20-05-2011

1

MTR Corporation, Hong Kong submits Report

10-March-2005

2

Planning Commission Approves

10-04-2007

3

Feedback sought from various Railway Departments.

(Engg., Electrical, Operating & Planning Departments)

21-06-2007

4

Feedback Received from Various Railway Depts.

Presentation & Discussions done with various Depts.

15-10-2007

5

Railway Board's (Delhi) Approval Sought.

23-10-2007

6

Railway Board Rejects the Above Request

16-11-2007

7

MRVC informs & invites Western Railway's (Mumbai) feedback.

02-06-2009

8

MRVC informs & invites Central Railway's (Mumbai) feedback.

02-06-2009

9

Railway Board (Delhi) Approves Request.

02-08-2010

10

MRVC MD's Approval Sought - MD raises some Points.

30-08-2010

11

MRVC's MD explained on points raised above - MD Approves.

08-09-2010

12

MRVC writes to World Bank.

24-09-2010

13

Railway Board adds Suggestions – Thus Some Modifications made.

03-11-2010

14

MRVC writes to Railway Board for final Approval.

23-09-2010

15

MRVC shares some more tech details with Railway Board.

06-12-2010

16

MRVC seeks World Bank's NOC.

18-02-2011

18

MRVC submits some Revisions for World Bank's NOC

28-March-2011


Journey of a Railway Report From 10-March-2005 to 28-March-2011

A Report Welcomed & Accepted by all the concerned Govt. Authorities

but the Decision Making Process lasts Six Long Years and continues to do so .....


  • Now, From March-2011 to September-2011, a Journey of another six months from above .....
Continued in Part IV .....

Best Regards,

Sunil.